Aptitude · 4 min lesson · 10 questions
Time and Work
Time and work questions ask how long a job takes when one or more people (or machines, or pipes) work on it. They look different on the surface, but they all rest on one idea: work is done at a steady rate. If you convert every statement into a rate, the problem becomes simple arithmetic.
The core idea
If someone can finish a whole job in n days, then in one day they finish 1/n of the job. That fraction is their rate. Work done = rate × time, and the whole job counts as 1.
So the time taken for a job at rate r is 1 / r.
Working together
When people work together, their rates add. If A takes a days and B takes b days, together they do 1/a + 1/b of the work per day, so the time together is
1 / (1/a + 1/b) = (a × b) / (a + b).
Example: A alone takes 12 days and B alone takes 36 days. Together: (12 × 36) / 48 = 9 days.
To find one person's time when the combined time and the other person's time are known, subtract rates. Example: A and B together finish in 15 days, and A alone takes 25 days. B's rate = 1/15 − 1/25 = 2/75, so B alone takes 75/2 = 37.5 days.
The LCM method
Fractions get untidy, so many people take the total work as the LCM of the given days. If A takes 10 days and B takes 15 days, let the total work be 30 units. Then A does 3 units a day and B does 2 units a day, together 5 a day, and the job takes 30 / 5 = 6 days. The units are imaginary, but they keep every number whole.
Alternate days and partial work
When people work in turns, find the work done in one cycle. A takes 10 days and B takes 15 days, and they work on alternate days starting with A. With 30 units of work, A does 3 and B does 2, so a two-day cycle completes 5 units. Six cycles finish 30 units, so the total is 12 days.
When a person joins later, work out how much has been done before they join, then use the combined rate for the rest.
Man-days
When the number of workers or hours changes, use man-days (or man-hours). The total work stays the same, so
M1 × D1 × H1 = M2 × D2 × H2
assuming all workers have the same efficiency. Example: 8 men finish a job in 15 days. How long would 12 men take? 8 × 15 = 12 × D, so D = 10 days. More workers mean fewer days.
If one person is, say, twice as efficient as another, their rates are in the ratio 2 : 1, and the time taken is in the ratio 1 : 2, so the faster one takes half the time.
Pipes and cisterns
This is the same idea with pipes. An inlet pipe fills a tank, so its rate is positive. An outlet pipe or a leak empties it, so its rate is negative. A pipe that fills a tank in 6 hours and a leak that empties it in 12 hours together fill at 1/6 − 1/12 = 1/12 per hour, so the tank fills in 12 hours.
Worked examples
Example 1. A can do a job in 14 days and B in 21 days. Working together, they take (14 × 21) / 35 = 8.4 days.
Example 2. A does a job in 24 days. He works for 8 days, then B finishes the rest in 10 days. A has done 8/24 = 1/3, leaving 2/3. So B does 2/3 in 10 days, and B alone would take 15 days.
Example 3. 10 men can do a job in 12 days working 6 hours a day. How many days do 15 men need if they work 8 hours a day? Man-hours = 10 × 12 × 6 = 720. Per day: 15 × 8 = 120. Days = 720 / 120 = 6.
Common mistakes
- Adding the days instead of the rates. Two people together are always faster than either alone.
- Forgetting that a leak or outlet has a negative rate.
- Mixing up days and hours when the working hours change.
- Leaving the total as 1 and carrying messy fractions when the LCM method would give whole numbers.
Exam tips
- Write each person's rate on the first line of the solution.
- Sense-check: the combined time must be smaller than the smaller of the two individual times.
- For efficiency questions, work in the ratio of rates rather than in days.
Now test yourself with the quiz below, and read each explanation to compare your method with the rate method.
Practice quiz: Time and Work
Pick an answer for each question. You will see the correct answer and the reason straight away. Your best score is saved on this device only.
-
A can finish a job in 12 days and B can finish it in 24 days. Working together, how many days do they need?
Together they do 1/12 + 1/24 = 3/24 = 1/8 of the job per day, so they need 8 days. -
A can do a job in 10 days and B in 15 days. How many days do they take together?
1/10 + 1/15 = 5/30 = 1/6 per day, so 6 days. -
A and B together can do a job in 12 days. A alone can do it in 20 days. How many days does B alone take?
B's rate = 1/12 − 1/20 = 2/60 = 1/30, so B takes 30 days. -
6 men can complete a job in 20 days. How many days would 10 men take to do the same job?
Man-days = 6 × 20 = 120. With 10 men: 120 / 10 = 12 days. -
A can do a job in 15 days. He works for 5 days, and B then finishes the rest in 10 days. In how many days could B do the whole job alone?
A does 5/15 = 1/3, leaving 2/3. B does 2/3 in 10 days, so the whole job takes B 10 ÷ (2/3) = 15 days. -
Pipe A fills a tank in 20 minutes and pipe B fills it in 30 minutes. If both are opened together, how many minutes does it take to fill the tank?
1/20 + 1/30 = 5/60 = 1/12 per minute, so 12 minutes. -
A pipe fills a tank in 6 hours, but a leak empties it in 12 hours. If both work together, how many hours does it take to fill the tank?
Net rate = 1/6 − 1/12 = 1/12 per hour, so 12 hours. -
12 men working 8 hours a day complete a job in 18 days. How many days will 9 men working 6 hours a day need?
Total man-hours = 12 × 18 × 8 = 1,728. Per day: 9 × 6 = 54. Days = 1,728 / 54 = 32. -
A is twice as efficient as B, and together they finish a job in 18 days. How many days would A take alone?
Let B's rate be x, so A's rate is 2x. Together 3x = 1/18, so x = 1/54 and A's rate is 1/27. A takes 27 days. -
A can do a job in 12 days and B in 18 days. A starts the work, and B joins him after 4 days. How many days in total does the job take?
In 4 days A does 4/12 = 1/3, leaving 2/3. Together they do 1/12 + 1/18 = 5/36 per day, so the rest takes (2/3) ÷ (5/36) = 4.8 days. Total = 4 + 4.8 = 8.8 days.